Southlake, Texas · Pool replacement & backyard construction
Southlake Pool Replacement & Backyard Transformation
H30 replaced an approximately 20-year-old pool and a four-person spa with a 43 × 23.5-foot pool, a 14 × 8.5-foot spa and connected outdoor gathering areas for a family of six in Southlake, Texas. Construction took approximately three and a half months.

- Pool dimensions
- 43 × 23.5 ft
- Spa dimensions
- 14 × 8.5 ft
- Spa jets & pumps
- 8 jets · 2 pumps
- Construction time
- Approx. 3½ months
The starting point
A backyard the family had outgrown.
The existing pool was approximately 20 years old, shallow and limited in both length and width. Its spa accommodated about four people. For a family of six that wanted to entertain, the layout no longer provided the space they needed.
This was not a tile-and-plaster refresh. H30 removed the old pool and spa and built a new layout around swimming, relaxing and gathering. Eight trees were removed as part of the work to make the yard more usable.
The goal was a complete backyard with different places for family and guests to spend time together—in the pool, in the spa and around the firepit.
New pool construction
43 feet of room to swim and gather.
The new pool measures 43 feet long and 23.5 feet wide. A large tanning ledge provides a place to spend time in shallow water, separate from the main swimming area.
A granite in-pool table creates another gathering spot within the water. Together, the ledge, seating and table give family and guests more than one way to enjoy the pool.
Because the original pool was removed, this project could be planned as new pool construction rather than a renovation limited to the old pool’s layout.
A more spacious spa
A larger spa with independent jet control.
The new spa measures 14 feet by 8.5 feet. Eight spa jets are served by two pumps, providing independent control of the jet systems.
A bi-level bench provides seating at different heights in relation to the jets. The larger footprint and seating arrangement make the spa a central part of the backyard, rather than the small addition it had been before.
Outdoor gathering areas
Connected spaces, from daylight to evening.
Stamped-concrete hardscaping connects the pool, spa and gathering areas. Marble coping and stone veneer around the spa, water-feature wall and firepit bring the finishes together. The in-pool table uses granite.
Pool lighting and overhead bistro lights extend the backyard into the evening. The firepit creates a gathering place outside the water, complementing the pool and spa rather than competing with them.
Explore H30’s outdoor-living services and hardscaping options for related project planning.
Beyond the visible finishes
The work beneath the finished backyard.
The scope included removing 1,600 square feet of existing driveway and installing approximately 200 linear feet of surface drainage.
Additional structural support using helical piers was also part of this project. The demolition, drainage and structural work supported the overall transformation alongside the new pool, spa, hardscaping and lighting.
Construction took approximately three and a half months for this backyard project.
The project in photographs
From demolition to evenings by the pool.
Browse the finished backyard and the construction work behind it. Select a photo to open the full-window gallery.

Pool, spa and firepit after dark
Illuminated pool and raised spa behind a firepit, with bistro lights overhead in Southlake.

Room to gather in the evening
The completed Southlake pool and raised spa illuminated beneath strings of bistro lights.

The new spa after dark
The raised spa and connecting pool lit at night, with surrounding stamped-concrete hardscaping.

A gathering place in the water
Granite in-pool table beside the seating area, with the raised spa and spillway beyond.

Removing the original pool
Demolition underway on the existing pool, with broken shell material and an excavator.

Shaping the new pool
Steel reinforcement and plumbing laid out inside the excavated pool before the shell is placed.

Two seating levels in the spa
The new spa shell showing its bi-level bench and jet plumbing during construction.

Installing the granite table
The granite in-pool tabletop installed before the surrounding pool interior is finished.

Preparing the surrounding hardscape
Reinforcement and formwork around the new pool and spa before concrete placement.

Drainage beneath the finished space
Surface-drainage pipe and an inlet being installed beside the driveway.

Connecting the pool and gathering areas
Fresh concrete surrounding the new pool and raised spa during hardscape construction.

Tanning ledge, seating and table
The tanning ledge, curved seating and granite in-pool table before the pool is filled.
The finished space
More room for a family of six—and their guests.
The new backyard brings together swimming, spa time, in-pool seating and evenings around the firepit. Replacing the undersized pool made room for a more versatile outdoor space, with multiple places to entertain and spend time together.
Project details
A few questions about this build.
Was the existing pool remodeled or replaced?
It was replaced. H30 removed the approximately 20-year-old pool and smaller spa, then built a new pool and spa as part of the Southlake backyard transformation.
What are the new pool and spa dimensions?
The pool measures 43 feet long by 23.5 feet wide. The spa measures 14 feet by 8.5 feet and includes a bi-level bench, eight jets and two pumps for independent jet control.
How long did this Southlake project take?
Construction took approximately three and a half months. That duration describes this project’s scope, not a fixed schedule for every H30 build.
What would you like your backyard to become?
Talk with H30 about your property, your priorities and the way you would like to use the space. Your initial consultation and proposal are free.